Civils Contractor Appointed
Construction Phase Underway
First Foundation Pour
Continued Civil Works
Q1 2026
PHASE 1 TOWER DELIVERIES COMPLETED
Q2 2026
BLADE DELIVERIES BEGIN
Q3 2026
fIRST TURBINE ERECTION
Q4 2026
44 fOUNDATION POURS COMPLETED